Last verified: 1 August 2026 for most entries. Entries reviewed 16 October 2026: Mohammed V terminal procurement and motorway projects. Status labels reflect publicly available evidence on the date shown for each entry. Official operators remain the authoritative sources for current passenger services. Update status lines when authoritative evidence changes.

A World Cup journey does not begin at the stadium gate. It begins when a visitor lands, finds the correct train or bus, reaches a city, checks into accommodation and travels to a match without confusion. If the next game is hundreds of kilometres away, the entire process begins again.

That is why transport may be Morocco's most complex infrastructure test for 2030. Six proposed host cities stretch from Tangier in the north to Agadir in the south. Their airports, railway stations, roads and urban networks do not begin from the same level of readiness. Some systems already carry passengers every day. Others are construction sites, procurement programmes or official plans whose real test has not yet begun.

This living tracker separates those categories. It does not treat a ceremony as an opening, a target as a guarantee or an architectural map as an operating service.

Independence notice. MoroccoMondial2030 is an independent editorial project of MoroccoPassport. It is not affiliated with or endorsed by FIFA, ONCF, ONDA, transport operators, the 2030 World Cup organizers, the FRMF or any government authority. Statuses reflect publicly available evidence on the last-verified date and may change. Official operators remain the authoritative sources for current passenger services.

How to read this tracker
Operating Carrying passengers now.
Under construction Physical works confirmed underway.
Contracted / Procurement Contract or tender confirmed; not yet operating.
Officially planned Announced by an authoritative institution with a stated programme.
Proposed / under study Discussed or studied without a confirmed operating service.
Status to verify Insufficient evidence for a stronger classification at last check.

Full Status Matrix — 20 Systems Tracked

System or project Status Verified description
Al Boraq — Tangier to Kenitra Operating Dedicated high-speed rail infrastructure operating since 2018. Africa's first high-speed rail service.
Rail service — Kenitra to Casablanca Operating Al Boraq trains continue toward Rabat and Casablanca over upgraded conventional tracks. The route from Kenitra southward is not dedicated high-speed infrastructure.
Kenitra–Marrakech LGV extension Under construction ONCF confirms a 430 km extension of the high-speed network toward Marrakech. Physical works are underway. Not operating; do not assign journey times as confirmed services.
New ONCF rolling stock — 168 trains Contracted / Procurement ONCF awarded procurement contracts for 168 new-generation trains. Fleet not yet in service; track separately from line completion.
Marrakech–Agadir rail extension Proposed / under study A longer-term strategic ambition discussed in official planning contexts. Do not combine with the Kenitra–Marrakech project currently under construction. No confirmed construction contract or active works independently verified at last review.
Casablanca metropolitan rail — three lines, 92 km Under construction Physical programme launched; scheduled for operation by 2030. Planned to connect Grand Stade Hassan II, Mohammed V Airport and Casa-Port. Not operating today.
Casa-Port – Mohammed V Airport express Officially planned Officially described with planned 15-minute frequency. Separately described from the three-line metropolitan programme; may share infrastructure. Not operating.
Casablanca tramway and Busway Operating Existing urban mass-transit foundation serving the city. Operating foundation for 2030 first/last-mile planning.
Rabat–Salé tramway Operating Two-line cross-city network operating between Rabat and Salé. Existing urban transit foundation.
Marrakech BHNS / bus system Operating High-level bus service corridors operating in Marrakech. Verify specific route coverage and expansion works before reporting expanded status.
Agadir Amalway BRT Operating Bus rapid transit system operating in Agadir. Verify exact operating corridor and relationship to proposed stadium transport before reporting.
National bus modernisation — 3,746 buses Contracted / Procurement National programme announced. Initial tenders reportedly included Fez, Marrakech, Tangier, Agadir and Benslimane. Procurement totals are not proof of delivered service; verify per-city fleet in service separately.
Mohammed V Airport — existing terminals Operating Morocco's principal international gateway, operating with existing terminal capacity.
Mohammed V Airport — new terminal Under construction ONDA stated a 20-million-passenger terminal was launched, with an announced delivery target of 2029. Not operating. Separate ONDA statements (February and April 2025) cited different total capacity targets (35M and 40M respectively); both are reported with their source dates, not merged.
Rabat–Salé Airport — new terminal Status to verify ONDA previously announced a terminal adding approximately 4 million passengers of annual capacity, with delivery expected after April 2025. Verify live operating status before publication; do not assign Operating without current confirmation.
Marrakech Menara Airport expansion Officially planned ONDA confirms major expansion programme. Verify project-specific construction status and completion before upgrading to Under construction or Operating.
Agadir Al Massira Airport expansion Officially planned ONDA confirms expansion activity at Agadir. Airport especially important given the absence of a passenger railway connection to Agadir. Verify construction phase before upgrading status.
Tangier Ibn Battouta and Fez–Saïss Airport expansions Officially planned Both airports included in ONDA's Airports 2030 programme. Tangier combines air, Al Boraq and ferry links to Europe. Fez–Saïss also linked to the national rail network. Verify per-airport works before assigning Under construction.
A31 Tit Mellil–Berrechid motorway Operating 30 km motorway connecting the Casablanca bypass (A1) at Tit Mellil to the Casablanca–Marrakech (A3) and Berrechid–Beni Mellal (A4) motorways. Opened 27 November 2025, delivered ahead of schedule, according to ADM. Also provides an alternative access route to Mohammed V Airport. This motorway opened before 2030 preparations; it is not a new October 2026 announcement. (Source: ADM press release, 27 November 2025.)
Rabat–Casablanca Continentale motorway Officially planned 60 km motorway announced as part of ADM's 2025–2032 investment programme (12.5 billion MAD total), signed 21 March 2025. Would connect the Rabat bypass (at Ain Atiq) directly to the Casablanca bypass (at Tit Mellil). Land expropriation financing protocol (1.2 billion MAD) signed at the same time; work contracts were reported in preparation in parallel. ADM's 2025–2032 programme covers the full period to 2032; not all components are on track to open before 2030. Do not describe this project as under construction or operating without independent verification of works status. (Source: ADM press release, 21 March 2025.)

The Operating Foundation

Morocco is not beginning with an empty map. Al Boraq, inaugurated in 2018, established the country's first high-speed railway and Africa's first operating high-speed service. Dedicated high-speed infrastructure runs between Tangier and Kenitra; Al Boraq trains continue toward Rabat and Casablanca over upgraded conventional tracks. The service turned the northern corridor into Morocco's strongest intercity transport spine.

Conventional ONCF services already connect Casablanca, Rabat, Tangier, Fez and Marrakech. Agadir remains outside the passenger railway network. Casablanca and Rabat–Salé operate tramways, while Casablanca also has Busway services. Marrakech and Agadir have developed higher-capacity bus corridors. All six host cities have airports or access to an airport serving their region.

This is real capacity, not a 2030 promise. But it does not yet form a complete World Cup network.

National Rail — North to South

Tangier ✈ Airport + Ferry Kenitra LGV starts here Rabat ✈ Airport Fez ✈ Airport Casablanca ✈ Mohammed V Marrakech ✈ Menara Airport Agadir ✈ Al Massira · No rail LEGEND Operating rail Under construction (LGV) Proposed / under study Conventional (operating) Host city (with airport) Host city (no passenger rail) Kenitra–Marrakech LGV Under construction

Schematic editorial map · Not for journey planning · Line positions are illustrative

Kenitra–Marrakech: The National Rail Project

The most consequential intercity project is the Kenitra–Marrakech high-speed extension. ONCF describes a 430-kilometre line extending the existing northern high-speed corridor toward Marrakech. Physical works are underway.

Its importance reaches beyond journey time. The project is intended to reorganize rail capacity through the country's busiest corridor, including Casablanca, and create space for new metropolitan and regional services on existing lines. For 2030, it could connect Tangier, Rabat, Casablanca and Marrakech within a much stronger north–south system.

The correct status is Under construction. Until passenger service begins and schedules are published, projected travel times remain targets rather than services supporters can book.

Exterior of Gare de Marrakech railway station showing the arched Moroccan-style entrance with palm trees and a traveller with luggage in the foreground.

Gare de Marrakech — Morocco's rail network currently terminates here. The Kenitra–Marrakech LGV under construction will extend high-speed services to this station when completed. Morocco's wider infrastructure transformation →

New Rolling Stock: 168 Trains

ONCF has awarded procurement for 168 new-generation trains. Rolling stock is an essential part of readiness: tracks alone cannot provide tournament-frequency service. The fleet programme carries Contracted / procurement underway status and should be tracked separately from line completion.

Promotional illustration of three ONCF new-generation train designs in a landscape setting.

⚠ Promotional illustration — not an editorial photograph of delivered rolling stock. ONCF awarded contracts for 168 new-generation trains. Entry into service has not yet been independently confirmed. Source: ONCF procurement announcement.

The Agadir Gap

Agadir presents the clearest break in the proposed host-city rail map. The city has an international airport, motorway access and urban transport, but no passenger railway.

Extending rail south from Marrakech toward Agadir has been discussed as a strategic ambition. It must not be confused with the verified 430-kilometre Kenitra–Marrakech project now under construction. Unless an authoritative source confirms a construction contract and active works for Marrakech–Agadir, this tracker retains Proposed / under study status.

That does not make Agadir inaccessible. It means aviation, road transport and organised tournament services will carry greater responsibility if rail does not reach the city before 2030.

Motorway Infrastructure

Morocco's motorway network already provides the intercity road spine that connects host cities. Two projects are relevant to the 2030 context.

The A31 Tit Mellil–Berrechid motorway (30 km) opened on 27 November 2025, according to ADM's official press release. It connects the Casablanca bypass (A1) to the Casablanca–Marrakech (A3) and Berrechid–Beni Mellal (A4) motorways at the Berrechid interchange, and provides an alternative access route to Mohammed V International Airport. ADM reported that the project, which cost 2.5 billion MAD and was built entirely by Moroccan firms, was delivered ahead of schedule. This is not a new 2030-period announcement; it is an operating road that opened before this review.

The Rabat–Casablanca Continentale motorway is an announced project included in ADM's 2025–2032 investment programme, the framework agreement for which was signed on 21 March 2025. The planned 60 km route would connect the Rabat bypass (at Ain Atiq) directly to the Casablanca bypass (at Tit Mellil). A land expropriation financing protocol of 1.2 billion MAD was signed at the same time, with ADM reporting that work contracts were being developed in parallel. ADM's overall 2025–2032 investment programme covers 12.5 billion MAD across multiple projects over the full period to 2032. Not all components of that programme are scheduled to complete before 2030. This project should not be described as under construction or operating until works status is independently confirmed.

Casablanca's Metropolitan Transformation

Casablanca is where national rail, airport access, urban transit and stadium transport converge. Official reporting describes a three-line metropolitan railway covering 92 kilometres and scheduled for operation by 2030.

CASABLANCA 2030 — PLANNED METROPOLITAN RAIL All routes — Planned for operation by 2030 · Not operating today Line 1 — planned Line 2 — planned Line 3 — planned CAS Casa-Port City centre station HSN Grand Stade Hassan II Under construction Benslimane Province CMN Mohammed V Airport Operating · new terminal U/C ✈ Express — 15 min planned Schematic diagram · Distances not to scale · Not for journey planning

All three metropolitan lines are planned for 2030 — none is operating today. Diagram is schematic and not geographically accurate.

Line 1 is planned between Grand Stade Hassan II and Mohammed V International Airport. Line 2 would connect the stadium with Casa-Port. Line 3 would link Casa-Port and the airport. Ten new stations are planned, while existing stations would be modernized. The system is designed for frequencies as high as one train every 7.5 minutes and an eventual 150,000 daily passengers.

A separate airport express has also been described between Casa-Port and Mohammed V Airport, with planned 15-minute intervals.

Grand Stade Hassan II lies outside central Casablanca in El Mansouria, Benslimane Province. Its success depends on high-capacity transport that is not yet carrying spectators. The metropolitan programme is one of the most important items in this tracker. Only completed stations, tested trains, published timetables and live passenger service will justify Operating status.

Airports 2030 — Six Host-City Gateways

Most international supporters will enter Morocco by air. ONDA's Airports 2030 strategy seeks to modernize infrastructure and passenger processing while expanding capacity across the national system.

Official figures require careful attribution. A February 2025 ONDA statement said Mohammed V Airport would increase from 14 million to 35 million passengers by 2029. An April 2025 ministerial statement referred to a modern terminal or airport plan reaching 40 million. This tracker records both statements with their dates rather than selecting whichever number sounds most impressive.

At national level, official reporting described a goal of roughly 80 million passengers of airport capacity by 2030. ONDA reported actual 2024 traffic of 32.7 million passengers. Traffic and designed capacity are different measures and are not interchangeable in this tracker.

Architectural rendering of the proposed Mohammed V Airport new terminal interior, showing a hexagonal-patterned ceiling, palm trees and passengers walking through a glazed concourse.

⚠ Architectural rendering — not a photograph of the completed terminal. ONDA stated a new 20-million-passenger terminal at Mohammed V Airport was launched and is targeted for 2029. Not yet operating. Source: ONDA Airports 2030 programme communications.

Casablanca
Mohammed V International (CMN)
Operating
New terminal U/C
Metro/Express planned

Morocco's principal international gateway. New 20M-passenger terminal targeted for 2029. Three-line metropolitan railway and airport express planned but not yet operating.

Marrakech
Menara Airport (RAK)
Operating
Expansion planned

One of Morocco's busiest tourism gateways. ONDA confirmed expansion works. The LGV under construction will bring high-speed rail to Marrakech for the first time. Verify per-component construction status.

Rabat
Rabat–Salé Airport (RBA)
Operating
New terminal — verify

Airport operating. ONDA announced a new terminal adding ~4M passengers of annual capacity. Delivery expected after April 2025. Verify live operating status before assigning Operating label to the new terminal.

Tangier
Ibn Battouta Airport (TNG)
Operating
Expansion planned

Tangier combines an international airport with Al Boraq and ferry links to Europe. ONDA includes expansion in the Airports 2030 programme. The critical integration challenge is high-capacity movement between airport, city, rail station and stadium.

Agadir
Al Massira Airport (AGA)
Operating
Expansion confirmed

Airport especially important given the absence of a passenger railway. ONDA confirmed expansion activity. Airport-to-city and airport-to-stadium transport will be a decisive part of Agadir's 2030 readiness. Verify construction phase.

Fez
Fez–Saïss Airport (FEZ)
Operating
Expansion planned

Fez has conventional rail and an international airport. Official reporting referred to airport capacity reaching 5 million passengers. Bus modernisation and reliable airport–stadium transfers will be central to match-day operations.

Host-City Urban Transport — Status Matrix

Host city Airport High-speed rail Conventional rail Tram / BRT Stadium access
Casablanca ✓ Operating (CMN) ◐ Planned 2030 ✓ Operating ✓ Tram + Busway ◐ Metro planned 2030
Rabat ✓ Operating (RBA) ✓ Al Boraq access via Kenitra ✓ Operating ✓ Tramway (R-S) ◐ Verify stadium route
Marrakech ✓ Operating (RAK) ◐ LGV U/C → 2030 ✓ Operating ✓ BHNS / bus ◐ Verify direct route
Fez ✓ Operating (FEZ) ✗ No Al Boraq ✓ Operating ◐ Bus / modernising ◐ Bus-dependent
Tangier ✓ Operating (TNG) ✓ Al Boraq (operating) ✓ Operating ◐ Bus / modernising ◐ Verify airport–stadium link
Agadir ✓ Operating (AGA) ✗ No rail network ✗ No rail network ✓ Amalway BRT ◐ Airport/road critical

✓ Operating  ◐ Planned / partial / verify before reporting  ✗ Not present. Matrix reflects status at last-verified date.

The First-and-Last-Mile Problem

Rabat–Salé tramway at a station platform with the distinctive curved Tour Mohammed VI skyscraper visible in the background under blue sky.

The Rabat–Salé tramway — one of Morocco's operating urban transit foundations. A fast intercity train cannot solve a journey if the final urban connection is slow or unclear. What AFCON proved about Morocco's transport readiness →

Intercity infrastructure brings supporters to a host city; urban transport determines whether they reach the stadium.

A fast train cannot solve a journey if the stadium connection is slow, inaccessible or unclear. The final kilometres require capacity, dedicated lanes where appropriate, pedestrian routes, accessible vehicles, multilingual signage, ticket integration and crowd-control plans.

Grand Stade Hassan II is the largest example, but the principle applies to every venue. Fez, Marrakech, Agadir and Tangier must connect large crowds with city centres, stations and airports. Rabat must integrate a high-capacity stadium with the capital's existing systems.

The 2030 test is not whether each city owns buses. It is whether thousands of people can leave a match simultaneously without creating unsafe queues or trapping ordinary residents in gridlock.

What AFCON Tested

What AFCON demonstrated on transport

  • Multi-city supporter movement without major reported organizational failure
  • International praise for transport links and tourism infrastructure in post-tournament assessments
  • Match-day crowd dispersal at six host cities tested under live tournament conditions
  • Existing tramways and bus networks absorbed tournament volumes in Casablanca and Rabat
  • Tangier's Al Boraq access provided a high-speed northern corridor for supporters

What AFCON could not test

  • Grand Stade Hassan II and its Casablanca metropolitan rail connections — not yet constructed
  • Kenitra–Marrakech LGV — not operating during AFCON
  • Mohammed V Airport new terminal — not yet delivered
  • Volume of a 48-team World Cup spread across six cities plus co-hosts in Spain and Portugal
  • Cross-border coordination and integrated multi-country transport booking

AFCON proved organisational capacity. Mission 7 measures whether the next generation of infrastructure achieves operational capacity before 2030.

Risks and Verification Watchlist

Risk 1 — Integration

Systems completing separately may not work as one journey

Railways, airports and city transport can each be completed while still failing to function as a coherent passenger experience. Physical completion of individual elements does not guarantee integration of ticketing, signage, timetabling or crowd flow.

Risk 2 — Timing

Opening immediately before the tournament leaves no recovery time

Infrastructure opening in late 2029 or early 2030 leaves minimal time for reliability testing, staff training and operational adjustment. Later-opening systems carry higher risk of tournament-period failures even if technically complete.

Risk 3 — Clarity

Promotional maps can blur operating lines and future corridors

This tracker will never draw operating and planned services in the same visual style without a status legend. Planned completion is not operational service. Target years are not guaranteed opening dates.

Risk 4 — Legacy

Tournament shuttles may not produce durable public transport

The strongest infrastructure projects are those that residents will continue using for work, education and family travel after 2030. Tournament-only solutions built to different standards than permanent services should be identified as such.

Risk 5 — Agadir

No passenger railway creates airport and road dependency

If no rail extension reaches Agadir before 2030, aviation and road transport must carry the full intercity supporter load. Tournament-period road capacity, parking, organized shuttles and wayfinding carry higher operational risk without a rail alternative.

Editorial Assessment

A National Network Under Construction

Morocco already possesses a transport foundation many hosts would envy: Africa's first high-speed railway, established international airports, operating tramways, a national rail network and modern motorways. The 2030 challenge is to connect that foundation at a larger scale. The Kenitra–Marrakech line must enter tested passenger service. Casablanca's stadium, airport and city must function as one metropolitan system. Airport expansions must become operational terminals rather than capacity announcements. Every host city must solve the final journey to the stadium. The ambition is credible because it builds upon systems that already work. The verdict remains deliberately unfinished: Morocco's 2030 transport network is not merely planned, and it is not yet complete. It is a national network under construction.

Living Tracker note. This page is designed to be updated as infrastructure status changes. When a project moves from Under construction to Operating, update the status badge, remove any "not yet operating" language, and update the Last verified date. Do not mark a service Operating until it carries passengers on a published timetable. Promotional maps and ceremony images are not evidence of operational status.

Independence notice. MoroccoMondial2030 is an independent editorial project of MoroccoPassport. It is not affiliated with or endorsed by FIFA, ONCF, ONDA, transport operators, the 2030 World Cup organizers, the FRMF or any government authority. Project status and event information may change; official bodies remain the authoritative sources.